Management & Coordination plan for the first Reporting period
(2006.01.01.
-2006.12.31)
|
1.Coordination & Management ativities necessary
to start the project (establishment
of the coordination office, money transfer to the partners, organization connections
between partners etc. ) |
January
-February 2006 |
|
2.Coordination
&Management activities necessary for preparation to the Introductory
Conference (organization of preparation the technical plans for
implementation the project tasks etc. ). Organization of the Introductory Conference. |
February -March
2006 |
|
3.Organization
of the Coordination Board Meeting |
March 2006 |
|
4.Establishment
of the project management & coordination plan (based on the plans of
Cluster management & Coordination plans and approved by partners) Report on the plan |
March 2006 |
|
5.Preparation
of shooting report on the
introductory Conference |
March 2006 |
|
6.The
management activities necessary for publishing the project booklet (based on materials
of the Introductory Conference) |
March –May 2006 |
|
7.Organization
of the Advisory Board Meeting |
May 2006 |
|
8.Organization
of the Coordination Board Meeting for monitoring the progress on implementation of the tasks settled |
June 2006 |
|
9.Management of
S&A activities in preparing reports on study of barriers women
scientists face in their career |
August
–December 2006 |
|
10.Coordination
&Management of the activities necessary for organization the job on creation
of the strategy |
August-
December 2006 |
|
11.Management&
Coordination activities necessary for preparations
to the Workshop in Tallin |
October-December
2006 |
|
12.Organization
of the Coordination Board Meeting on the results obtained by S&A
activities |
October-December
2006 |
|
13.Coordination
&Management Activities on the
development o regional data basis and monitoring system “Women in Sciences
and HT in Lithuania and Baltic States” |
March 2006-
November 2007 |
|
14.Coordination
&Management the activities for preparation the Midle term report |
September December 2006 |
|
15.Coordination
&Management activities for dissimination
the project results as well as for exchange of good practice
(participation in the conferences, creation of Dinamic web site, etc.) |
May-December 2006 |